The execution process has been divided in 5 stages, completely planned according to the LEAN principle so that our activities can take place just-in-time. The mounting process for averagely 4 doorways per execution stage will be completed within one week, and then they will be wind and waterproof.
Nigtevechthof upgrade
18 doorways02/11/2016
In Amsterdam Holendrecht, we have continued the upgrade process of the Maasdrielhof and Nigtevechthof neighborhood. In this stage, Vroom will be placing 18 doorways, made out of white concrete, and 9 poured concrete floors for the entrances.