46-box garage park

100 CFA piles283 m¹ foundation

The GaragePark formula is a huge success. The boxes sell big and therefore, new parks are being built on a regular basis, this time in Purmerend. This garage park consists of 46 units for private users.

Vroom has realized the complete foundation for GaragePark. Inserting CFA piles, applying prefab foundation beams and taking care of the complete dimensioning process has all been done by us.

Clean-up

The soil was polluted and has therefore been cleaned up before the piling activities began. The polluted soil had been stored on-site causing the execution to be divided in two parts as a result of a lack of space.

Prefab units

The garage units have also been fully prefabricated and placed upon the prefab foundation beams. The advantage of prefab is that it gains a lot of time: all units have been placed within a few days. Subsequently, the paving around the units has been placed and the park has been opened.

46-box garage park
46-box garage park
46-box garage park
46-box garage park
46-box garage park
46-box garage park
46-box garage park
46-box garage park

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Sandro Pronk

Sandro Pronk

Share project:

Realization
18-12-2014 to 27-02-2015
Location
Purmerend
Client
Garagepark Nederland
 
Dick Reijnders
Project Manager

Can we help you with your project?